Kenya: UPDATE ON IFO II EXTENSION - NOVEMBER 2010

Attachments

Current situation

The development of infrastructures for the delivery of services by the agencies and demarcation of blocks/plots for settlement of refugees is rapidly progressing in Ifo II. Despite the heavy rains that hindered easy access for trucks that are delivering construction materials to all construction sites, most of the infrastructures that are funded under 2010 budget are expected to be completed by end of December 2010. The main road leading to Ifo II and all inter-camp roads require major improvement to ensure easy access for the delivery of construction materials and relief supplies in the near future. Preliminary talks were held with WFP SO-Dadaab on the possibility of joint funding for improvement of the roads after an assessment and cost estimate is done by LWF.