Informing humanitarians worldwide 24/7 — a service provided by UN OCHA

Iraq + 1 more

Iraq: RRP6 Monthly Update - April 2014: Shelter

Attachments

APRIL HIGHLIGHTS:

• 1650 refugees benefited from the construction of 330 tent foundations and cooking areas In Domiz Camp/Duhok :

• The improvement of the reception center is ongoing and about 90%. complete, as well as the construction of a soccer field is ongoing. The construction of a PHC is 98% complete, only minor works are pending. In Gawilan/Duhok :

• 108 tent foundation, 70 sanitation units and 32 cesspools are completed. In Qushtapa/Erbil :

• 464 tent foundation were completed and 6 prefabs for UN-offices have been installed incl. sun shades. In Basirma/Erbil :

• The distrbution area is 80% complete as well as fence and concrete slab for the new warehouse is complete.

• Concrete slabs are complete for the youth and women center.